Absence of Master List of Pre-Qualified Beneficiaries

National Housing Authority · 2022

Severity: HighRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: ComplianceIssue: Non-compliance

The projects were supposed to be community-driven, but in over half of the contracts, there was no list of who the intended low-income beneficiaries were. This means the projects may not truly serve the people they were meant to help.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"11 out of 21 contracts have no submitted master list of pre-qualified beneficiaries. The absence of the master list of pre-qualified beneficiaries signifies that the contract was not community-based as it fails to identify the beneficiaries who are eligible to benefit from the project."