Non-compliance with loan interest payment schedule and improper transfer of unused loan budget

Baliwag City · 2024

Severity: HighRecommendation: Unknown

What Happened?

Category: Financial ManagementIssue: Non-compliance

The city did not follow the planned payment schedule for its loan interest and moved the leftover money to the general fund instead of using it for the loan.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"Regarding the ongoing loan payment, the allocated budget for loan interest totaling ₱35,374,863.70 and the anticipated loan payment schedule were not followed, as payment dates were adjusted. As of year-end, only ₱8,502,819.07 had been paid, and the remaining balance was treated as savings and transferred to the GF."

Source Document

BaliwagCity2024_Audit_Report.pdf

Baliwag City · 2024 AAR · 3 files