Several funded projects not implemented

Baliwag City · 2023

Severity: ModerateRecommendation: Unknown

What Happened?

Category: OperationsIssue: Performance Issue

The city received funds from national agencies for 13 projects, but by the end of the year only 5 were done, 3 were still in progress, and 5 had not started, so residents did not get the intended services or benefits on time.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"Out of 13 PPAs funded from fund transfers received by the City from various NGAs, five PPAs were fully implemented, three were ongoing, and five were not yet implemented as of Dec. 31, 2023. Thus, the City's constituents were not able to prompltly enjoy the benefits to be derived from the ongoing and unimplemented projects."