Absence of As-Built Plan and Test Results
Pulilan · 2021
Severity: HighRecommendation: Unknown
What Happened?
Category: InfrastructureIssue: Deficient DocumentationThe municipality did not have as-built plans and material test results for construction projects.
Why It Matters
Recommended Actions
- Require the (a) MA to (i) submit to the Audit Team the DVs and SDs for the transactions totaling ₱8,442,871.31 for post-audit
- And (b) BAC to (i) send notices in writing to at least three observers before each procurement activity
- (ii) post the advertisement, notices of award and approved contract at the PhilGEPS and at prescribed places
- And (iii) require from the prospective bidders the submission of NFCC , SLCC and Statement of Completed and On-going Private and Government Contracts
- And (c) ME to submit the lacking supporting documents for progress and final billing particularly the as -built plans and test results of construction materials.
Original Audit Finding Excerpt
"Absence of as-built plan and results on test analysis of construction materials. This is not consistent with Section 9.1.1 of COA Circular No. 2012-001 which provides the additional documentary requirements common to all infrastructure projects."