Incomplete Construction Logbook

Pulilan · 2021

Severity: ModerateRecommendation: Unknown

What Happened?

Category: InfrastructureIssue: Deficient Documentation

The construction logbook was incomplete, missing important details about work progress and equipment.

Why It Matters

Recommended Actions

  • Require the (a) MA to (i) submit to the Audit Team the DVs and SDs for the transactions totaling ₱8,442,871.31 for post-audit
  • And (b) BAC to (i) send notices in writing to at least three observers before each procurement activity
  • (ii) post the advertisement, notices of award and approved contract at the PhilGEPS and at prescribed places
  • And (iii) require from the prospective bidders the submission of NFCC , SLCC and Statement of Completed and On-going Private and Government Contracts
  • And (c) ME to submit the lacking supporting documents for progress and final billing particularly the as -built plans and test results of construction materials.

Original Audit Finding Excerpt

"The submitted construction logbook mentioned only the number of manpower, the weather and the general description of the activity. Other items relating to work progress were not indicated such as the status of the on-going activity, new works started, name, size, and type of all major pieces of construction equipment at the site each day indicating whether these are operational or not, and if operational whether it is idle, and the reason why, number of supervisory and non-supervisory personnel on site, and visitors to the site."

Source Document

10-Pulilan2021_Part2-Observations_and_Recomm.docx