Misuse of Marawi Rehabilitation Trust Fund for Purposes Not Specified in the MOA

National Housing Authority · 2023

Severity: HighRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Financial ManagementIssue: Non-compliance

The money meant for rebuilding Marawi was spent on things not allowed by the agreement, like land development and housing units instead of schools and evacuation centers. Some funds were also given to the local government for unauthorized purposes, and some projects were paid twice from different sources. Also, a large amount that was supposed to be used for schools and vehicles was not spent at all.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"Although majority of the MRRRP Trust Fund on projects were disbursed for the rehabilitation of Marawi City, the same are not the specified purposes in the MOA, thus, contrary to Section 6, General Provision of the GAA for FY 2023, Sections 4(3) and 84(2) of PD No. 1445 and MOA between OP and NHA."

Source Document

11-NHA2023_Part2-Observations_and_Recom.docx

2023 AAR · 15 files