What Happened?
Category: Financial ManagementIssue: Non-complianceA budget allocation for a relocation project was cancelled and then reclassified under a different category, which may indicate improper fund management.
Why It Matters
Recommended Actions
No recommendations are available for this finding yet.
Original Audit Finding Excerpt
"The original allotment for the North Triangle Relocation Project amounted to P450 million. However, the amount of P286.702 million was cancelled by DBM and subsequently provided a supplemental appropriation of the same amount for CY 2014, which was reclassified under Other Releases."