Unauthorized Start of Construction Without Building Permit
National Housing Authority · 2024
Severity: HighRecommendation: Unknown
This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.
What Happened?
Category: Construction ManagementIssue: Non-complianceThe agency let the contractor begin building before getting the necessary permits, which caused the project to be halted and delayed.
Why It Matters
Recommended Actions
- Comply with the provisions of Sections 301 and 303 of the IRR of the National Building Code of the Philippines (PD No. 1096);
Original Audit Finding Excerpt
"Thus, NHA Management allowed the contractor to start the construction of the project without the required building permit."
