Failure to Impose and Deduct Liquidated Damages

National Housing Authority · 2024

Severity: HighRecommendation: Not Implemented

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Financial ManagementIssue: Non-compliance

Contractors who finished projects late did not have penalties deducted from their payments as required by procurement rules, and some penalties were calculated incorrectly.

Why It Matters

Recommended Actions

  • Reassess the computation of LD for the delays incurred by the concerned contractors to ensure compliance with the prescribed provisions of the RIRR and verify that the correct amounts are collected from their claims
  • And

Original Audit Finding Excerpt

"Agency Action Plan Reason for = Partial/Delay/ Ref. Audit Observations Audit Recommendations ; Target Implementation Status of Non- Action Taken/Action to be Action Plan Person/Dept. Date Implementation Implementation, Taken Responsible From To if applicable necessary demand letters were issued. RO coordinated with the AD in regarding the final computation of claims of the contractor's liability to pay the final computations by AD of the unrecouped advances and excess payment and collect/deduct the same from their progress billing to other region. CY 2023 Liquidated damages (LD) were | b.ii, Initiating —_termination/ Not Implemented Reg 6: To expedite the completion AAR not applied, recovered, or | rescission of contracts on Accounting of the housing units, the Observation | deducted from the payments to | infrastructure projects when Department District/Regional Office No. 14, contractors who incurred | liquidated damages reach 10 recommends the imposition of page 180 | delays rangi"