Non-compliance with RA 9184 leading to terminated housing projects

National Housing Authority · 2024

Severity: HighRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Project ManagementIssue: Non-compliance

The housing agency did not follow procurement rules, leading to many projects being stopped before completion, wasting money.

Why It Matters

Recommended Actions

  • To prevent termination of future projects, Implementing Unit shall strictly monitor the status and progress of works and any occurrence of slippages must be communicated immediately to the Contractor to ensure that the housing project shall be completed within the timeframe set

Original Audit Finding Excerpt

"The above observations regarding terminated projects due to the incurrence of more than 15 per cent negative slippage and legal issues on land titles, were not prevented due to non-compliance with the prerequisites of RA No. 9184 and its RIRR."

Source Document

11-NHA2024_Part2-Observations_and_Recomm.doc