Variation Orders Not Reflected in Approved Procurement Plan

National Housing Authority · 2024

Severity: HighRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Procurement PlanningIssue: Non-compliance

The project cost went up due to changes, but the official procurement plan was not updated to show this, which violates the rules.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"The Audit Team noted that the cumulative variation order resulted in a revised contract cost of P6.055 million, which exceeds the ABC of P5.571 million. Review of supplemental/amended APP for FY 2024 showed that no record or entry reflecting the said Variation Order, indicating non-compliance with procurement planning and budget alignment requirements."