Dormant Advances to Contractors totaling P518,493,182.67

Department of Public Works and Highways · 2024

Severity: HighRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Financial ManagementIssue: Weakness

The agency had over P518 million in old advance payments to contractors that had not been recovered. It sent demand letters and asked permission to write off a small part.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"Existence of dormant account balances of Advances to Contractors account– P518,493,182.67"