1,435 Infrastructure Projects Not Completed Within Contract Time
Department of Public Works and Highways · 2024
This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.
What Happened?
Category: Project ManagementIssue: Non-complianceThe DPWH failed to complete more than a thousand public works projects on schedule, costing the government over 77 billion pesos, and forcing communities to wait longer for roads, schools, and other infrastructure.
Why It Matters
Recommended Actions
No recommendations are available for this finding yet.
Original Audit Finding Excerpt
"Review and evaluation of different DPWH infrastructure projects revealed that 1,435 projects with a total cost of P77,432,245,841.61 were not finished/completed within the specific contract time or original target completion date."