Non-reclassification of completed Construction in Progress to appropriate PPE accounts

Department of Public Works and Highways · 2024

Severity: HighRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Financial ManagementIssue: Non-compliance

Thousands of finished construction projects were still recorded as 'under construction' in the accounting system, and some project-related costs were left in the wrong account, making the financial statements inaccurate.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"An audit of the CIP accounts of the following DPWH Offices disclosed that 11,613 completed projects with an aggregate amount of P 333,723,099,462.31 were not reclassified or transferred to the appropriate infrastructure asset accounts"