Infrastructure Projects Started Construction 67 to 100 Days After Notice to Proceed
Department of Public Works and Highways · 2024
Severity: ModerateRecommendation: Unknown
This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.
What Happened?
Category: Project ImplementationIssue: Non-complianceContractors were given the go-ahead but waited two to three months before actually starting work, delaying project completion and wasting public time.
Why It Matters
Recommended Actions
No recommendations are available for this finding yet.
Original Audit Finding Excerpt
"Infrastructure projects commenced construction only after 67 to 100 days from receipt of NTP."