Completed infrastructure projects not turned over to recipient agencies

Department of Public Works and Highways · 2024

Severity: HighRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Financial ManagementIssue: Non-compliance

The agency built roads, buildings, and other projects but did not formally hand them over to the intended users because paperwork was lost or not filed, so the assets remain on the agency's books even though users may already be using them.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"The non-turnover of completed infrastructure projects to end -users or recipient agencies was primarily due to missing turnover documents, which were lost or damaged during office transfers and renovations. As a result, the Accounting Division could not dereco gnize the projects from the books. Additionally, lack of coordination between units concerned and failure to submit required documents such as Property Transfer Receipts (PTRs) and Journal Entry Vouchers (JEVs) further delayed the proper turnover and accou nting, despite the projects already being in use by the recipients."

Source Document

09-DPWH2024_Part2-Observations_and_Recomm.pdf