What Happened?
Category: ComplianceIssue: Non-complianceThis district office missed the deadline for submitting its gender plan and accomplishment report, which prevented auditors from checking whether its GAD spending was correct.
Why It Matters
Recommended Actions
No recommendations are available for this finding yet.
Original Audit Finding Excerpt
"I Pangasinan 1st DEO GPB and AR not submitted within the reglementary period, hindering the audit and evaluation of GAD alignment."