High aggregate variation orders in multiple projects
Department of Public Works and Highways · 2024
This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.
What Happened?
Category: Project ManagementIssue: Non-complianceThe district office made many changes to projects that cost over 22 million pesos. These changes were due to poor planning and lack of updated information. If the engineers had done proper surveys before starting, many of these changes could have been avoided.
Why It Matters
Recommended Actions
No recommendations are available for this finding yet.
Original Audit Finding Excerpt
"Despite the guidelines, Nueva Ecija 2nd DEO had variation orders within the contract time with an aggregate amount of P22,901,211.94, accounted for in 39 infrastructure projects of the District. The District gave some/ various reasons for the variation orders. However, the reasons showed the non-updating of the Planning Section of the current conditions surrounding the proposed projects ahead of the actual implementation. Prior to procurement, the assigned engineers could have done appropriate surveys and investigations to determine any situations and conditions for adjustment in the plan, when warranted, thus, could have avoided the preparation of variation orders."