What Happened?

Category: Financial ManagementIssue: Non-compliance

The final contract prices were higher than the official estimated project costs approved by the Commission on Audit.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"The contract costs were found to be higher than the COA total Estimated Cost."

Source Document

09-DPWH2024_Part2-Observations_and_Recomm.pdf