What Happened?
Category: Financial ManagementIssue: Non-complianceMany completed government projects have not been formally handed over to the agencies that should use them, and the accounting records are therefore incomplete.
Why It Matters
Recommended Actions
No recommendations are available for this finding yet.
Original Audit Finding Excerpt
"For the remaining balance, the Certificate of Turnover and other documents were not yet forwarded to the Accounting Unit by the Implementing Offices, thus recording of the transfer was not yet made."