Material unit costs used in POW, ABC and DUPA differed from Construction Materials Price Data

Department of Public Works and Highways · 2024

Severity: HighRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Financial ManagementIssue: Non-compliance

The project budget and price analysis used material prices that did not match the official government price data, potentially overstating costs.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"The preparation of POW, ABC and Detailed Unit Price Analysis (DUPA) for the infrastructure project utilized a different material unit cost from those reflected in the quarterly issued Construction Materials Price Data."