SiPAT logo

SiPAT

Liquidated Damages Not Imposed or Under-Collected for Delayed Projects and Goods

Department of Public Works and Highways · 2024

Severity: HighRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Financial ManagementIssue: Non-compliance

Contractors and suppliers who finished projects or delivered goods late were not charged the penalty required by law. Some penalties were collected but were less than they should have been, costing the government money it was entitled to receive.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"Liquidated damages were not imposed, collected , or deducted from the payments made to the contractors and suppliers who incurred delays ranging from 1 to 1,075 days corresponding to days elapsed between the target schedule and actual dates of completion of projects and delivery of goods, with a total c ontract cost of P5,109,276,235.99. Moreover, liquidated damages collected totaling P474,743.76 in 13 projects of two DPWH Offices were found to be lower by P1,817,754.45 than the COA validated or evaluated amount of P2,292,498.21."

Source Document

09-DPWH2024_Part2-Observations_and_Recomm.pdf

2024 AAR · 13 files