SiPAT logo

SiPAT

Under-collection of liquidated damages

Department of Public Works and Highways · 2024

Severity: HighRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Financial ManagementIssue: Non-compliance

The agency collected much less in late fees from contractors than it should have, and in some cases did not collect at all, leaving the government deprived of money it was owed for delays.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"Moreover, it was also noted that LD imposed and collected by the Management totaling P474,743.76 in 13 projects of two DEOs were found to be lower than the COA validated amount of P2,292,498.21, resulting in under collection of P207,220.16."

Source Document

09-DPWH2024_Part2-Observations_and_Recomm.pdf

2024 AAR · 13 files