114 Unimplemented or Not-Yet-Started Projects Worth P6.73 Billion
Department of Public Works and Highways · 2024
This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.
What Happened?
Category: Project ManagementIssue: Non-complianceBillions of pesos worth of approved infrastructure projects had not even broken ground, often because funds were released late, permits were delayed, or the same project was accidentally listed more than once.
Why It Matters
Recommended Actions
No recommendations are available for this finding yet.
Original Audit Finding Excerpt
"As at year-end, there are 114 projects across several DPWH offices that have yet to start implementation, with a total cost of approximately P6,725,010,239.94, as shown in Table 64."
