Semi-expendable property misclassified as PPE not fully implemented

Department of Public Works and Highways · 2024

Severity: HighRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Financial ManagementIssue: Non-compliance

Items that cost too little to be considered fixed assets were incorrectly labeled as property and equipment; the correction is still incomplete in several offices.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"In Albay 2 nd DEO and Camarines Sur 5 th DEO, reconciliation of the other PPE Accounts is still ongoing. In Zamboanga del Sur 2nd DEO, the Finance Section is still awaiting for the List of Semi -Expendable Reports from the Supply Unit, which will serve as the basis for transferring the PPEs to its proper Semi-Expendable account."

Source Document

10-DPWH2024_Part3-Status_of_PYs_Recomm.pdf