Capital outlays underutilized by ₱316.9 billion or 34.4% of final budget

Department of Public Works and Highways · 2023

Severity: HighRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Financial ManagementIssue: Performance

The agency spent only about two-thirds of the money it had set aside for buildings, roads, and other capital projects, leaving roughly ₱317 billion unspent. This means many planned projects may have been delayed or not carried out at all.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"Capital Outlays 874,608,971,000.00 920,353,249,260.00 603,440,332,843.67 316,912,916,416.33"