What Happened?

Category: Project ImplementationIssue: Deficiency

Some completed roads have missing sections, making them unusable and requiring more money to fix.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"Completed infrastructure projects were unusable due to gaps in road component. These items include widening and concreting of approach roads, among others, which require additional cost/funding."