What Happened?

Category: ProcurementIssue: Non-compliance

The agency paid for goods before they were formally inspected and accepted, which violates rules against advance payments.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"Payments of goods were made before inspection and acceptance."