Category: Procurement ComplianceIssue: Non-compliance

The office rushed the evaluation of bids and verification of the winning bidder. They are now required to follow the prescribed time limits.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"In the case of Infrastructure, the maximum duration of bid evaluation is 7 days, while post qualification for the bidder with the lowest calculated responsive bid is 45 calendar days from the receipt of bids. In this particular case, the BAC TWG conducted both activities for only 9 days."