Unsettled Right of Way claims

Department of Public Works and Highways · 2023

Severity: HighRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Project ImplementationIssue: Non-compliance

The government owed money to property owners for land used in infrastructure projects, but failed to pay them on time, even after the projects were finished. This caused hardship for the claimants.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"Claims on the acquisition of R ight of Way in the total amount of P338,029,196.16 for the implementation of infrastructure projects of DPWH Regional Office No. XI and Davao City D istrict Engineering Office remained unsettled/unpaid contrary to Section 17.6 of the Revised I mplementing Rules and Regulations of Republic Act (RA) No. 9184 and Section 6 of RA No. 10752; thus, benefits accruing to the claimants were delayed."

Source Document

09-DPWH2023_Part2-Observations_and_Recomm.pdf

2023 AAR · 13 files