P90.17 billion in projects not completed on time

Department of Public Works and Highways · 2023

Severity: HighRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Project ManagementIssue: Non-compliance

More than 90 billion pesos worth of government infrastructure projects were not finished on time. Many district offices have only partially dealt with the delays, and some contractors have not been fully penalized.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"Par. 13 Delayed completion and non-implementation of projects a) Projects not completed within the specific Contract time – P90,175,886,852.06"