Regional Office X: 14 Completed Projects Remaining in CIP Without Completion Certificates

Department of Public Works and Highways · 2023

Severity: HighRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Financial ManagementIssue: Non-compliance

Fourteen finished construction projects were still listed as 'under construction' in the office's books because the official completion certificates had not been issued.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"For Regional Office X, out of 75, the remaining 14 completed projects which are still included in the CIP accounts have no Certificate of Completion yet. A request will be sent to Construction Division."