Non-imposition of liquidated damages on delayed projects and goods delivery

Department of Public Works and Highways · 2023

Severity: HighRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Financial ManagementIssue: Non-compliance

The government did not charge contractual penalties to contractors and suppliers who finished projects or delivered goods late, as required by their contracts. The auditors told them to do so, and DPWH offices are working on it, but many have only partially complied, meaning the government may have lost money that should have been collected.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"Page 246 of 508 AGENCY ACTION PLAN AND STATUS OF IMPLEMENTATION Ref. Audit Observation Audit Recommendation Agency Action Plan Status of Implementation Reason for Partial/ Delayed/ Non- Implementation, if applicable Action Taken/ Action to be Taken Action Plan Person/Dept. Responsible Target Implementation Date From To • CS- CP 2: Updating of Master Plan and Feasibility Study of Flood Control for Panay and Agusan River Basin - Package II Reason/s for Delay: Difficulty in the conduct of Social Survey (Non - Technical) Action Plan: Instructed the Consultant to consistently follow -up and coordinate with LGU and project affected people. • Infrastructure Preparation and Innovation Facility Reason/s for Delay: - Rectification of Design Plans and Reports, incorporating the comments of DPWH and ADB. - Updating the FS report of Jalaur River Basin, taking into consideration the Stakeholders recommendations. Action Plan: - Close coordina"