SiPAT logo

SiPAT

Benguet 2nd DEO Delayed Submission of Disbursement Vouchers

Department of Public Works and Highways · 2023

Severity: ModerateRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Financial ManagementIssue: Non-compliance

The office had not given the auditors 17 payment vouchers worth over 94 million pesos, and it was still working to get them submitted.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"Page 339 of 508 AGENCY ACTION PLAN AND STATUS OF IMPLEMENTATION Ref. Audit Observation Audit Recommendation Agency Action Plan Status of Implementation Reason for Partial/ Delayed/ Non- Implementation, if applicable Action Taken/ Action to be Taken Action Plan Person/Dept. Responsible Target Implementation Date From To RO X Bukidnon 1st DEO Misamis Oriental 1st DEO South Cotabato 1st DEO Partially Implemented Fully Implemented Fully Implemented South Cotabato 1st DEO – Fully Implemented as delay will be mitigated in the submission of documents. 1,052,367,180.04 Only one (1) out of 26 contracts has not been submitted to COA amounting to 4,899,103.28 80,326,350.72 All 28 contracts have been submitted to COA. 1,707,987,611.70 Approval of DOLE’s booklet/ certificate and IC of Performance Bond and CARI are reasons which caused delay in the submission of contra"

Source Document

DPWH2023_AAPSI.pdf

2023 AAR · 13 files