Splitting of Procurement to Avoid Public Bidding

Department of Public Works and Highways · 2023

Severity: ModerateRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Procurement ComplianceIssue: Non-compliance

The agency broke up a large purchase into smaller parts to avoid holding a public bidding process, which is against procurement rules.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"No public bidding was conducted by the Agency for the procurement of its goods due to splitting of its procurement into different portions/dates as a result of insufficient planning and poor implementation of programs and activities."