Unrecouped Advances from Terminated/Rescinded Projects

Department of Public Works and Highways · 2023

Severity: HighRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Financial ManagementIssue: Non-compliance

The department paid contractors advance money for projects, but when those projects were cancelled, it did not get the money back. Many district offices have recovered only a small portion, leaving over P351 million outstanding and at risk of loss.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"b) Unrecouped advances from terminated/rescinded projects – P351,735,468.10"