SiPAT logo

SiPAT

MASELCO did not respond to liquidation demands

Department of Public Works and Highways · 2023

Severity: ModerateRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Financial ManagementIssue: Non-compliance

The district office repeatedly asked an electric cooperative to report on how it spent transferred money, but the cooperative never responded or provided any accounting.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"Page 146 of 508 AGENCY ACTION PLAN AND STATUS OF IMPLEMENTATION Ref. Audit Observation Audit Recommendation Agency Action Plan Status of Implementation Reason for Partial/ Delayed/ Non- Implementation, if applicable Action Taken/ Action to be Taken Action Plan Person/Dept. Responsible Target Implementation Date From To City DEO, Benguet 1st DEO, Benguet 2nd DEO, Upper Kalinga DEO, Mt. Province 1st DEO, and Mt. Province 2nd DEO Ifugao 1st DEO Ifugao 2nd DEO Lower Kalinga DEO Cagayan 2nd DEO Fully Implemented Fully Implemented Fully Implemented Fully Implemented Ifugao 1st DEO Undisbursed amount was due to non- payment of some vouchers that were processed on the last day due to lack of some important documents that forced the management to revert the allocated fund. It is ensured that there will be no reve"

Source Document

DPWH2023_AAPSI.pdf

2023 AAR · 13 files