Delayed project implementation due to unresolved right-of-way issues and missing RROW/parcellary budget components
Department of Public Works and Highways · 2023
This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.
What Happened?
Category: Project ManagementIssue: Operational DeficiencyRoad projects were held up because the land corridors (rights-of-way) were not obtained, and the project budgets had not set aside money for acquiring those corridors or for the required parcel surveys.
Why It Matters
Recommended Actions
No recommendations are available for this finding yet.
Original Audit Finding Excerpt
"delay in the implementation of the projects. Zamboanga City DEO - Management have already discussed among themselves how to address these issues on RROW. They explained that the RROW acquisition for some terminated infrastructure projects which were re-bidded was initiated by the DPWH Region IX, but were eventually turne d-over to ZCDEO. They added that some of these projects did not have RROW and parcellary components in the budget allocation."