What Happened?

Category: Financial ManagementIssue: Non-compliance

The office had not submitted 45 payment vouchers out of the 222 that the auditor checked, so a fifth of the vouchers were missing.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"Mindoro Oriental - 77.48% 45 Disbursement Vouchers are still unsubmitted as of today out of 222 Disbursement Vouchers as identified by the COA in their AOM."