Delayed Submission of Infrastructure Contracts to COA

Department of Public Works and Highways · 2023

Severity: HighRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Financial ManagementIssue: Non-compliance

The agency sent two large construction contracts to the government auditor one day after the deadline. One of these was a P2.37 billion contract for the New Senate Building, which is a significant breach of the required submission period.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"211,753,172.96 – Delayed for 1 day in the submission of contract to COA 2. UPMO – BSPMC – Hilmarc’s Construction Corporation – P2,375,254,934.32 – Delayed for 1 day in the submission of contract to COA"