Right-of-way issues causing project delays
Department of Public Works and Highways · 2023
This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.
What Happened?
Category: ComplianceIssue: Non-complianceConstruction was held up because the government couldn't get the right of way—permission to use the land. In one district, 22 projects were delayed for this reason, and a telephone pole blocked one project. In another area, property owners changed their minds, causing legal disputes.
Why It Matters
Recommended Actions
No recommendations are available for this finding yet.
Original Audit Finding Excerpt
"RROW problems attributable to the delayed completion of the 22 projects, except for 1 project, were already resolved."