Unrefunded pay item for tree furnishings and transplanting

Department of Public Works and Highways · 2023

Severity: ModerateRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Contract ManagementIssue: Unliquidated collection

Contractors were supposed to refund costs related to trees that were removed or not provided, but only a small portion was refunded. The rest was recorded as money owed by contractors.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"Out of the 7 projects identified with an aggregate amount of P970,965, 3 contractors have refunded the cost of the Pay Item of Work -Tree Furnishings and Transplanting totalling to P101,890.00 with O.R. No 1170049 dated 02/06/2024 amounting to P82,980.00 and O.R. No. 1170048 dated 02/06/2024 amounting to P19,000.00 and Check No 628801 dated 7/29/2024 amounting to P40,000.00 while one project (23PE0021 amounting to P6,300.00 were removed on the rejoinder of COA."