What Happened?

Category: Project ImplementationIssue: Suspended

Several construction projects are still stopped because of land access, road right-of-way issues, and other on-site problems.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"CS3: Suspended due to ROW problem: absence for solar water projects"