Project suspension and realignment due to pending environmental compliance certificate

Department of Public Works and Highways · 2023

Severity: ModerateRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Environmental ComplianceIssue: Non-compliance

A project was put on hold because it had not yet received the required environmental permit. After talking with the environment department, the route was changed to avoid a protected mangrove forest.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"For project ID No. 23KJ0046 amounting to P47,529,999.36, only work suspension order No. 1 was applied on the project until such time that the environmental compliance certificate (ECC) will be approved. After various consultations with the Department of En vironment and Natural Resources (DENR) it was resolved that the project will be realigned such that it will no longer travers the Malaubang -Bagumbang Mangrove Swamp Forest Reserve (MBMSFR)."