Notices to Proceed issued before contract signing

Department of Public Works and Highways · 2023

Severity: ModerateRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Procurement ManagementIssue: Non-compliance

The agency issued go-ahead notices to contractors before the contracts were actually signed, violating proper procurement sequencing.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"The audit observation regarding the 2 projects that the NTPs were issued before signing of contracts were already complied in the succeeding procurement process."

Source Document

DPWH2023_AAPSI.pdf

2023 AAR · 13 files