Full payment and retention released despite missing roadway lighting

Department of Public Works and Highways · 2023

Severity: HighRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Financial ManagementIssue: Non-compliance

A contractor was paid everything it was owed, including the retention, before a required piece of work (roadway lighting) was done. The work was still missing during an audit inspection, and it was only finished later.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"Considering that this item can easily be installed, the PE allowed the contractor to collect the 100% and the 10% retention. When the COA personnel conducted inspection of this project on January 16, 2024, the missing Roadway lighting has not yet been installed as the item replacement was not yet available. However, on January 24, 2024, the contractor had already installed the missing Roadway Lighting."