Slope protection works constructed at different stations outside project limits

Department of Public Works and Highways · 2023

Severity: HighRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Project ImplementationIssue: Deviation from approved plans

Road slope repair work was done in different locations than originally planned because the planned areas were not actually dangerous. The engineers moved the work to steeper slopes that needed protection.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"Page 391 of 508 AGENCY ACTION PLAN AND STATUS OF IMPLEMENTATION Ref. Audit Observation Audit Recommendation Agency Action Plan Status of Implementation Reason for Partial/ Delayed/ Non- Implementation, if applicable Action Taken/ Action to be Taken Action Plan Person/Dept. Responsible Target Implementation Date From To Bacolod City DEO Benguet 1st DEO June 2024 August 2024 Bacolod-Fully Implemented Fully Implemented unretrieved steels. JEV Nos. are as follows: JEV-2024-05-002635 JEV-2024-07-003684 Payment of overtime pay services for FY 2023 was inappropriately charged against the EAO funds. Justification letter was submitted to the Office of the Resident Auditor. Moreover, JEV No. 2024-08-004605 dated August 27, 2024 was made to recognize the payment of employees on the Overtime Pay. Ben"