Eastern Samar DEO delayed implementation of 17 infrastructure projects
Department of Public Works and Highways · 2023
This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.
What Happened?
Category: Project ManagementIssue: Non-complianceIn Eastern Samar, 17 infrastructure projects worth about 873 million pesos were significantly delayed, with delays ranging from 15 days to 541 days. Some projects were still ongoing at the time of reporting, and penalties for late completion are being charged to contractors.
Why It Matters
Recommended Actions
No recommendations are available for this finding yet.
Original Audit Finding Excerpt
"During the ocular in spection conducted by the Audit Team, it was observed that the completion of the seventeen (17) projects were already delayed for the period ranging from 15 to 541 calendar days."