Dormant Balances in Advances to Contractors

Department of Public Works and Highways · 2023

Severity: HighRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Financial ManagementIssue: Non-compliance

The agency paid contractors in advance for projects, but many of these advances were never settled or collected. Almost 518 million pesos has been sitting in the accounts for years, and the agency does not know how to close them out.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"Review and analysis of the balances of Advances to Contractors accounts revealed that advance payments for 111 projects of various DPWH Offices aggregating P518,493,182.67 had been dormant for over 3 to 10 years."