Billions in retention money released before project completion

Department of Public Works and Highways · 2023

Severity: HighRecommendation: Unknown

This summary was generated automatically from the source document and may contain errors. It is not an official interpretation and should not be relied upon as legal guidance. Review the original excerpt and source document to verify before citing or acting on it.

What Happened?

Category: Financial ManagementIssue: Non-compliance

The agency released over a billion pesos in retention money to contractors before the projects were finished or accepted, which violates the rules. At least one district office only partially corrected the problem.

Why It Matters

Recommended Actions

No recommendations are available for this finding yet.

Original Audit Finding Excerpt

"Retention money aggregating P 1,360,849,819.89 pertaining to 182 infrastructure projects were released to contractors prior to the completion and/or final acceptance of the projects that were not implemented/ completed on schedule or satisfactorily undertaken contrary to item 6, Annex “E” of the same Revised IRR"